Newmont Mining Corporation 8-K
PositiveEarningsGuidance reaffirmed
Higher gold prices lifted earnings despite lower output; Cadia’s seismic event weighed on production and raised unit costs.
Filed 2026-07-23 16:05 ET
- 2.02 Results of Operations
- 9.01 Financial Statements and Exhibits
Summary
Q2 2026 results with the company remaining on track to achieve its previously published FY2026 guidance. Higher realized gold prices lifted sales and earnings Y/Y despite lower gold production; the Cadia seismic event weighed on production and drove higher unit costs.
Key Figures
| Metric | Q2 2026 | Q2 2025 | Y/Y |
|---|---|---|---|
| Sales | $6.12B | $5.32B | +15% |
| Attributable gold production | 1.29 Moz | 1.48 Moz | -12% |
| Average realized gold price | $4,414/oz | $3,320/oz | +33% |
| Net income attributable to Newmont stockholders | $2.20B | $2.06B | +6.8% |
| Adjusted net income, non-GAAP | $2.25B | $1.59B | +41% |
| Diluted EPS | $2.06 | $1.85 | +11% |
| Adjusted diluted EPS, non-GAAP | $2.10 | $1.43 | +47% |
| Net cash from operating activities | $2.92B | $2.38B | +23% |
| Free cash flow, non-GAAP | $2.21B | $1.71B | +29% |
- Gold by-product costs applicable to sales (CAS) were $1,043/oz and all-in sustaining costs (AISC) were $1,621/oz. Both rose sharply Q/Q as lower gold and co-product volumes, the Cadia downtime, higher royalties and diesel prices pressured unit costs.
- The company ended the quarter with $9.0B cash, $13.0B total liquidity and $3.4B net cash. Since the prior earnings call, it returned $1.9B through dividends and repurchases, including $1.7B in repurchases; $4.3B remains on the $6B authorization. Since February 2024, the share count has fallen by more than 100M shares, or approximately 9%.
- The declared Q2 dividend is $0.26/share, payable 9/28/2026 to holders of record 9/3/2026.
Guidance
| Metric | Period | Guidance | Prior | Direction |
|---|---|---|---|---|
| Attributable gold production | FY2026 | 5,260 koz | — | — |
| Gold by-product CAS, non-GAAP | FY2026 | $1,055/oz | — | — |
| Gold by-product AISC, non-GAAP | FY2026 | $1,680/oz | — | — |
| Sustaining capital | FY2026 | $1.95B | — | Reaffirmed |
| Development capital | FY2026 | $1.4B | — | Reaffirmed |
| Copper production | FY2026 | 102 kt | — | — |
| Silver production | FY2026 | 32 Moz | — | — |
| Lead production | FY2026 | 90 kt | — | — |
| Zinc production | FY2026 | 220 kt | — | — |
| Exploration and advanced projects expense | FY2026 | $525M | — | — |
| General and administrative expense | FY2026 | $375M | — | — |
| Interest expense, net of capitalized interest | FY2026 | $175M | — | — |
| Depreciation and amortization | FY2026 | $2.815B | — | — |
| Reclamation and remediation accretion | FY2026 | $385M | — | — |
| Adjusted tax rate | FY2026 | 33% | — | — |
| Capitalized interest | FY2026 | $175M | — | — |
| Attributable production weighting | H1/H2 2026 | 49% / 51% | — | — |
| Sustaining capital weighting | H1/H2 2026 | 42% / 58% | — | — |
| Development capital weighting | H1/H2 2026 | 37% / 63% | — | — |
| Total portfolio reclamation spend | FY2026 | ≈$850M | — | — |
| Yanacocha water-treatment plant reclamation spend | FY2026 | ≈$550M | — | — |
| Yanacocha water-treatment plant total spend | Project total | ≈$1.8B | — | — |
| Reclamation spend after water-treatment work | 2028 | $300M-$400M | — | — |
| Cash dividend commitment under capital allocation framework | Annual | $1.1B | — | — |
| Indicated annualized dividend per share, not declared | Current indicated rate | $1.04 | — | — |
The FY2026 guidance estimates carry a ±5% range; the company says it remains on track to meet them. Q3 attributable gold production is expected to be broadly in line with Q2, while unit costs are expected to rise, partly offset by higher co-product volumes. Production is weighted to H2, with the increase driven primarily by Boddington, Tanami, Lihir, Cerro Negro and Brucejack. Reclamation spend is elevated by Yanacocha water-treatment work.
Investor Takeaways
- Q3 production versus the expected Q2-level result, and unit costs versus the expected increase, will indicate how operations and spending timing are tracking.
- H2 delivery against the production and capital weightings will be important to achieving the FY2026 outlook.
- Watch for a final investment decision on Red Chris Block Cave as the project advances following regulatory approvals.