Applied Digital Corp. 8-K

PositiveEarnings

New HPC take-or-pay leases expanded the contracted buildout; tenant fit-outs and rental launches drove revenue growth.

Filed 2026-07-27 17:04 ET

Summary

Q4 and FY2026 results, alongside HPC lease and financing updates. Revenue growth reflected tenant fit-out services and the launch of HPC data-center rentals, while the company reported wider GAAP losses. Applied Digital signed three 15-year take-or-pay leases for 810 MW, representing ≈$20B of base-term contracted revenue; its total contracted portfolio reached ≈1.41 GW and ≈$36B over base terms, or ≈$86B with renewal options. It also completed the separation of its cloud services business and held approximately 96% of ChronoScale at fiscal year-end.

Key Figures

Metric Q4 FY2026 Q4 FY2025 Y/Y
Revenue $259M $51.1M 407%
Adjusted revenue, non-GAAP $240M $38.0M 532%
Operating loss $(125)M $(44.1)M 183% wider loss
Net loss attributable to common stockholders from continuing operations $(111)M $(53.1)M 108% wider loss
Adjusted net income, non-GAAP $12.9M $(7.6)M n/m
Adjusted EBITDA, non-GAAP $42.4M $0.98M 4,220%
Diluted EPS $(0.39) $(0.24) 63% wider loss
Adjusted diluted EPS, non-GAAP $0.04 $(0.03) n/m
Metric FY2026 FY2025 Y/Y
Revenue $611M $229M 167%
Adjusted revenue, non-GAAP $540M $144M 274%
Operating loss $(236)M $(72.2)M 228% wider loss
Net loss attributable to common stockholders from continuing operations $(249)M $(234)M 6.7% wider loss
Adjusted net income, non-GAAP $36.1M $(12.5)M n/m
Adjusted EBITDA, non-GAAP $107M $19.6M 447%
Diluted EPS $(0.91) $(1.16) 22% narrower loss
Adjusted diluted EPS, non-GAAP $0.11 $(0.06) n/m
Operating cash flow $89.7M $(115)M n/m
  • Q4 HPC Hosting revenue was $203M, including $152.4M from tenant fit-out services, and segment operating profit was $26.2M. Data Center Hosting revenue was $37.3M vs $38.0M a year earlier, with $12.5M of segment operating profit.
  • FY-end cash, cash equivalents and restricted cash were $4.2B, and debt was $5.0B. FY property and equipment purchases and other asset purchases were $2.87B.
  • The company issued $2.15B principal of 6.750% senior secured notes due 2031 at 98% of par to fund 200 MW at Polaris Forge 2. Subsequent to quarter-end, it issued $1.59B of 7.000% senior secured notes due 2031 at par to repay a $300M bridge facility and fund a 150 MW building at Polaris Forge 1. Its revolving facility was subsequently upsized to $430M committed plus a $120M accordion.

Guidance

No guidance in this filing.

Investor Takeaways

  • Watch construction and commissioning against the stated initial operations timelines: calendar 2027 for Delta Forge 1 and Polaris Forge 3, and the first half of 2028 for Delta Forge 2.
  • Phase 1 of Polaris Forge 1’s second building (75 MW) reached Ready for Service on 6/30/2026, bringing live campus capacity to 175 MW; future delivery progress will test the company’s ability to execute its contracted buildout.